Wednesday, April 16, 2008

Public Notice Bridge Closing















The Charles Berry Bridge will be closing June 5-August 29th
for electrical maintenance and repair.

The Bridge will be open for the following events:
The Lorain International Festival
June 27-29, 2008

Fourth of July Fireworks
July 4, 2008

The Port Fest
July 18-20, 2008

Bridge Address:
103 East Erie Ave
Lorain Ohio 44052

You can monitor the Buckeye Traffic website www.buckeyetraffic.org for the most current information. Here is the planned schedule as outlined at the pre-construction meeting held this week:

  • Daily Lane Closures from 9:00 a.m. to 3:00 p.m., Monday through Friday
  • Complete Closure June 5 to June 26; July 7 to July 17; and July 21 to August 28 (or longer to complete the required work).

Any questions please contact the ODOT public information officer
Brian Stacy
419-207-7182

No comments: